Wednesday, 9 January 2013

Project Report - Great River Ouse Bridge

Out in the dark again, I am sure some of our guys are developing echo location and the ability to hang upside down by their feet ............ actually ;o)

Today's project report is a short one about a pretty large Principal Inspection.  It included a delamation (hammer tap) survey and concrete testing of the 7 span Great River Ouse Bridge near King’s Lynn for Atkins.
Hammer testing all surfaces
The testing comprised 8 No. test panels to the soffit and 4 panels to each of two piers.  We chose to use an underbridge unit, as the most effective means of gaining access to the soffit above the river and waterlogged spans.

No comments:

Post a Comment